Liquid cooled Plumbing scheme of energy storage tank
abstract:The first level liquid cooling main pipe adopts ID50mm metal pipe or PE pipe, with a total length of about 15-20 meters;
The secondary liquid cooling pipeline adopts PA pipes with ID21mm or ID25, with a total length of about 40 meters
The first level liquid cooling main pipe adopts ID50mm metal pipe or PE pipe, with a total length of about 15-20 meters;
The secondary liquid cooling pipeline adopts PA pipes with ID21mm or ID25, with a total length of about 40 meters;
The third stage liquid cooling pipeline adopts an ID14mm PA pipeline, with a total length of about 80 meters;
The connection method adopts SAE, VDA, or CQC quick plug connection.
The secondary liquid cooling pipeline adopts PA pipes with ID21mm or ID25, with a total length of about 40 meters;
The third stage liquid cooling pipeline adopts an ID14mm PA pipeline, with a total length of about 80 meters;
The connection method adopts SAE, VDA, or CQC quick plug connection.